29th December 2024


Work Undertaken for D1013 "B" End Bogie - as at December 2024

On Friday, 20th September 2024, D1013's B end bogie was relocated from the TMD Pit Road to No.3 road in the TMD, accomplished by using the 08 to drag/push the bogie. There was a bit of a lash up of wooden sleepers to aid this on the front of the bogie, to act as a buffer.

Once D1013 had arrived on No.3 Road there has literally been hundreds of man hours spent removing 50+ years of 'baked' on brake dust and railroad dirt, at this point I would like to say a very big thank you to all the volunteers who have done any scraping. The frames are being 'scraped' back to bare metal revealing original paintwork, the bare areas are then being coated with red oxide primer, this will eventually be coated with Chassis Black.

The WLA Team have also started to remove component parts; the first items removed were the Drive Shafts, a little 'gentle' persuasion was required, once they were out of the way, the Thrust Brackets were lifted from the Bogie - these brackets are basically used to push the loco along.

Following our in-house procedure, the next items for removal were the Equalising Beams but before attacking these items, measurements were taken for the Primary Spring heights. The 4 Primary Springs were released and then lifted clear of the Bogie. The Primary Springs sit on top of the Axlebox and there is a Locator between the Spring and the Axlebox; this Locator has a Manganese Liner welded to it - it was common for the weld on these to fail and we have evidence of this.

The first Equalising Beam proved quite 'easy' to remove as one of the Pedestal Brackets that supports the Beam in position had 'fallen' apart, a lack of weld penetration during the construction of the Bracket being the cause.

The second Beam proved a lot more difficult to remove and needed more 'gentle' persuasion to get it out.  The 2 Equalising Beams have subsequently been taken to our Bridgnorth workshop for assessment and dismantling. The 2 Brake Cylinders serving the Centre axle were also removed.

Attention then moved to unbolting and lifting out the Intermediate Gearbox, which was removed.

The 2 Brake Cylinders serving the Inner axle were the next items to be removed, also at the same time the last 2 Primary Springs which were released and lifted clear of the Bogie. Removing the Primary Springs has exposed the Spring Hangers, one of which has virtually 'welded' itself in place, after much soaking in oil and more 'gentle' persuasion this Spring Hanger has now been removed.

This concludes work undertaken to date!

****************

Outstanding Work for D1013 "B" end Bogie - as at December 2024

Bogie Frame

    Scrape, Clean and Prime Paint – on-going (certain areas to be identified that just need scraping and cleaning).
    Identify areas (welds) requiring Non-Destructive Testing (NDT) and carry out NDT testing, to be carried out in conjunction with Torque Arm rubber replacement (see below) – sub-contract involvement required for certification purposes.
    Write procedure/s, carry out repairs to any welds identified by NDT – only required if faults found, will require sub-contract qualified Welder.
    Primary spring pocket recess edges – build up with weld and dress back areas worn away by Primary Springs rubbing – qualified welder required.
    Prime paint and Finish paint (Black) complete framework.

    Brake Rigging – removed / in-situ

    Scrape, clean, prime and finish paint (Black) – on-going.
    Refit all removed rigging (timing of this to be advised)– new fasteners required.

    Intermediate Gearbox

    Drain oil, remove Oil Pump for inspection, repair if required and refit.
    Casing exterior – scrape, clean, prime and finish paint (Black).
    Refit to Bogie.

    Equalising Beams – 2 off

    Items currently at Bridgnorth in a stripped-down state.
    NDT of central pivot weld – sub-contract involvement required for certification purposes.
    Weld ‘top hat’ bushes in place around central pivot - sub-contract qualified Welder required working to WLA established procedure (includes weld NDT).
    Re-assemble Equalising Beams complete – new pins, bushes and bearings in-stock, awaiting arrival of new Spring Hangers (on order).
    Pedestal Bracket – new grease pipes to manufacture and silver solder in position – SVR ESMP (Bridgnorth workshop) currently undertaking this work.
    Refit Equalising Beams to Bogie frame.


    Brake Cylinders – 6 off

    Transfer to WLA Bridgnorth workshop.
    Brake cylinder seals – new seals on order.
    Strip, clean, inspect, rebuild and air test each cylinder.
    Clean, prime and finish paint (Black).
    Refit to Bogie frame – new fasteners required.
    Carry out Air test.

    Spring Hangers – 4 off loose, 4 off captive

    Remove from bogie frame – on-going.
    Thoroughly clean to remove all debris from threads and shank (see Whatsapp photo for example), threads to have die-nut run down them (1.5/8” BSW to confirm).
    NDT inspect each spring hanger - sub-contract involvement required for certification purposes.
    Refit to bogie frame. (Loose washer to be tack welded in position).
    Spare spring hangers to clean and NDT test – currently located in store at Bridgnorth.

    Thrust Brackets – 2 off

    Scrape, clean and prime paint – on-going.
    Rear Thrust Bracket – new rubbing plate and fasteners required – sub-contract manufacturer to source – on-going.
    Rear Thrust Bracket – rebuild with new rubbing plate and fasteners.
    Front and Rear Thrust Brackets to clamp in position to Loco underframe, drill / ream out existing mounting holes, manufacture new location bolts – this work to be carried out in conjunction with SVR ESMP and requires the locomotive to be on the Lifting Jacks.
    Finish paint (Black).

    Hydraulic Dampers / Brackets – 2 off

    Dismantle end fittings from removed Dampers and fit to refurbished Dampers – refurbished Dampers in-stock.
    Damper Brackets - Scrape, clean, prime of finish paint (Black).

    Lateral Side Reaction Brackets – 2 off

    Scrape, clean, prime and finish paint (Black) – only metal sections require painting.

    Primary Springs – 6 off

    Scrape, clean and protect removed Primary Springs with preservative for possible future use and store away in container.
    Fit new Primary Springs to Bogie frame – items in-stock.

    Drive Shafts – 3 off

      Items removed from bogie to be stored away in container.
      Fit new Drive shafts to bogie – items in-stock.

      Air Piping

        Scrape, clean, prime and finish paint (White) – on-going.

        Torque Reaction Arms – 3 off

          Scrape, clean and prime paint – on-going whilst in-situ.
          Dismantle, inspect and assess Torque Reaction Arm sandwich plate trunnions, replace existing Torque Reaction Arm rubbers and rebuild – TMD side pit required when the Bogie is mobile – new Rubbers in stock.
          Finish paint (Black) Reaction Arms.

          ****************

          Thank you

          Graham Gant

          Please note the above information complete with photographs, may be seen from the PDF Article by CLICKING HERE

          Outstanding Work for "B" end Bogie may be seen from the PDF Article by CLICKING HERE

          Featured Photo by Sally Sheldon

          Category: 
          Western Locomotive Association 50 Years

          The WESTERN LOCOMOTIVE ASSOCIATION is a company limited by guarantee - Registered No: 3873466
          Registered Address: 5, Prospect Place, Millennium Way, Pride Park, Derby, England DE24 8HG. Charity No. 1115058