Second (and largest) WLA Order placed for D1013's bogie overhaul!

19th February 2024

Following the WLA's recent order for bogie Pedestal Brackets, a further order has been placed for 16 Bogie Spring Hangers which will be specially forged by WH Tildesley Ltd, one of the leading forged component manufacturers in the UK, based in Willenhall, West Midlands.

The Spring Hangers are safety critical components, subject to wear and tear over the years. They are located on the Compensating Beams, four per bogie, which means that the WLA will have 8 spare (it was almost just as expensive to manufacture a minimal quantity of 8, compared to 16!).

The total order value was just over £20k, which included part-cost tooling of £4.7k. The lead time for the order is expected to be around 20 weeks and will financed from the D1013's Bogie Appeal. Additional items for D1013's bogies overhaul project will be:

  • Torque Reaction Rubbers
  • High Tensile Bolts for Torque Reaction Arms
  • Separation Tubes for the Torque Reaction Arms
  • Brake Cylinder components

This new order is the biggest one ever placed by the WLA since the "B" end transmission overhaul project for D1062 back in 2007 (financed by the HLF). The two recent orders have been financed through generous donations from D1013's Bogie Appeal. The two recent orders will reduce the Bogie Appeal from approx. £29k to around £3k, so any donations to help with the above would be much appreciated at:

D1013 Bogie Appeal

Thank you!

Category: 
Western Locomotive Association 50 Years

The WESTERN LOCOMOTIVE ASSOCIATION is a company limited by guarantee - Registered No: 3873466
Registered Address: 5, Prospect Place, Millennium Way, Pride Park, Derby, England DE24 8HG. Charity No. 1115058